Scope of Balaji |
||
Required Machines for plant |
Qty |
Kw |
Four Bin Inline Batching Plant |
1 |
3.73 |
Material Transfer Conveyor |
1 |
2.24 |
Bi directional Transfer Conveyor |
1 |
2.24 |
Cement screw conveyor with hopper |
2 |
7.46 |
Vibrating Table |
4 |
5.97 |
Planetary colour layer mixer 3.0 |
1 |
3.73 |
Planetary concrete layer mixer 4.0 |
1 |
5.60 |
Auto Water Dispenser |
2 |
1.49 |
Auto admixture Dispenser |
2 |
0.75 |
Mixer platform Stand |
2 |
0.00 |
Panel Board (Controlling system) |
1 |
0.00 |
Concrete auto Dispenser |
1 |
7.46 |
Colour auto Dispenser |
1 |
4.48 |
hydraulic Pallet stacker |
2 |
0.00 |
Mold Demolder |
1 |
15.00 |
Total |
|
60.13 |
Scope of Customer |
|
Plant Civil work requirments |
Value |
PCC Shed for Machines (L x W x H) (feet) |
80 x 40 x 16 |
Cabinet for controlling panels |
15 x 20 x 10 |
Coverd area for 1st day curing |
1500 Sqft |
Raw material storage space |
1500 Sqft |
Mold storage room |
300 Sqft |
Cement storage room |
300 Sqft |
Finished goods storage space |
2000 Sqft |
Labour hatment space |
700 Sqft |
Office and other |
500 Sqft |
water tank |
100 Sqft |
Total |
10000 Sqft |
Wodden pallets 900 x 900 x 16 mm |
900 |
Rubber / PVC / plastic molds |
11000 Nos |
Production Requirments |
|
Required labours for plant |
Numbers |
Tractor loader operator |
1 |
Panel bord operator |
1 |
Cement loader |
1 |
Colour dispencer operator |
2 |
Concrete dispencer operator |
2 |
Laveler |
1 |
Unloading from vibrator table |
1 |
mold transportation to cuering area |
1 |
demolding and laquer quoting |
5 |
Total |
15 |
vehical loading unloading extra |
5 |
Air compressor 3.0 Hp |
1 |
Oil for mixer gear boxes ( Liters) |
100 |